Plumbing and Stuff
After many days of work, the rough plumbing (drain-side) is done with the exception of two connections. It is ready for inspection. We are supposed to start on the PEX supply lines tomorrow.
The bank has approved us spending money on a new framing crew (the previous one was fired) to finish the framing and siding. The bank also said we could have money to hire a roofer. The framing is supposed to take 8 days, starting tomorrow, and the roofing should start Wednesday and be done by Friday. After all the hold-ups (this set of hold-ups), progress is finally being made (again)... How many times have I said that?
Some of the drains in the laundry room and master bath
The boys' bathtub
No comments:
Post a Comment
If you want us to know your opinion, go ahead!