Friday, September 21, 2007

House Update

Well, it looks like the ball is rolling again.
We have a quote from a new SIPS company, SureTight (www.suretight.com), and we will be signing the contract and delivering the deposit on Monday or Tuesday. They are supposed to create panel drawings for us to approve, and once they are approved, they will have the panels to us within 3 to 4 weeks.
In the meantime, the foundation should start being built, and once that is complete, the first floor framing will be put in. After that is done, the panels can be put up, and hopefully with about a week's worth of work, we will have a "dried in" house.
Once some real work starts, I'll start posting pictures for all to see.

No comments:

Post a Comment

If you want us to know your opinion, go ahead!